Project Flow

Five phases. One living sanctuary.

The development of Casa das Águas Sagradas unfolds through interconnected phases that transform the land, the infrastructure, and the community — each one built on the last.

  1. Phase 1
    01

    Foundations & Essential Infrastructure

    Land registration, technical planning, borehole drilling, water reservoir, ecological sanitation, generator, and access pathways.

  2. Phase 2
    02

    Eco-Accommodation & Operational Structures

    One large yurt, four eco-bungalows, dry toilets, biodigesters, and the first communal areas. The retreat receives its first guests.

  3. Phase 3
    03

    Regenerative Land Development

    Large-scale native reforestation, soil restoration, regenerative agriculture, and water management — swales, ponds, natural filtration.

  4. Phase 4
    04

    Community Development & Expansion

    Ceremonial space, community kitchen, learning center, and partnerships with facilitators, healers, and regenerative practitioners.

  5. Phase 5
    05

    Consolidation & Long-Term Sustainability

    Monitoring ecological impact and well-being. The sanctuary becomes self-sustaining — economically, socially, environmentally.

Next 12 months

12-Month Goal

Complete the essential infrastructure to welcome 11 people sustainably.

  • Drinking water (well, pump, tank, filtration)
  • Ecological sanitation
  • Solar energy + batteries
  • Lodging: 1 large yurt + 3 glamping
  • Outdoor kitchen and showers
  • Structural repair of the house
  • Bio-construction workshop
  • Initial reforestation
Budget transparency

Laying the foundations — Phase 1

The first phase establishes the structural and energetic base of the project. Every euro is accounted for.

Orientación solar del terreno — Algarve interior, Portugal
Mapa del terreno — Casa Das Águas Sagradas, Monchique

Phase 1 — Foundations

  • Topographic plan€750
  • Borehole drilling 7" (70–100 m)€4,500
  • Borehole widening 10" (5–12 m)€7,800
  • APA licensing€335
  • Submersible pump DAB S4 2/20 (1.5 CV)€2,750
  • Water tank TV 12,500 L (vertical)€2,850
  • Compact septic system FC 8,000 L (25 people)€3,950
  • Electric generator€5,055
  • Machinery for entrance opening & cleaning€6,500

Phase 2 — Eco-Accommodation

  • Eco-accommodation€76,000
  • Sanitation systems€34,000
  • Communal structures€31,000
  • Labor & installation€22,000

Once the essential systems are in place, the retreat is capable of receiving its first guests and generating initial revenue.

Current fundraising goal

Total we are raising: €199,900

Phase 1 + Phase 2 — the investment needed to lay the foundations of the sanctuary.